Enter your BAC, EV, PV and AC below — the calculator returns every PMI / ISO 21508 earned-value KPI instantly. No signup, no email. If you want these numbers updating live across your whole project, start free with WBSync — 30-day trial, up to 30 active operatives, no card required.
30-day trial, up to 30 active operatives. No card required.
SPI = EV ÷ PV. Above 1.0 = ahead of schedule. Below 1.0 = behind. PMI considers SPI unreliable past ~80% complete; for late-stage projects, use Earned Schedule instead.
CPI = EV ÷ AC. Above 1.0 = under budget. Below 1.0 = overrun. PMI guidance: once CPI drops below 1.0 past 20% complete, it rarely recovers without intervention.
This calculator uses the most common formula: EAC = BAC ÷ CPI. Three other PMI-recognised formulas exist; see the glossary entry for when to use each.
The cost performance the team must achieve on remaining work to land on BAC. TCPI > 1.10 is generally regarded as unrecoverable without scope, resource or rate intervention.