4 min read · Updated 15 Jun 2026
What it measures
Every daily plan commits a number of crew-hours — crew size × hours per person across the activities on it. Plan compliance compares that planned figure against the approved hours that landed on those same activities, across the last 30 days. Above 100% means more got worked than planned; below means the plan is slipping.
Approved-only, on purpose
The KPI counts approved hours and nothing else. Draft and submitted entries don't move it, and — importantly — the hours correction a PM can make when closing a plan never feeds it either. That correction fixes the plan's own record; the compliance number stays anchored to what was genuinely approved, so it can't be talked up at close-out.
Where to find it
Plan compliance sits in the KPI grid alongside % complete, S/E, SPI, CPI and EAC. It shows the percentage, the number of plans in the window, and the hours behind it.
The tile links straight to the project's daily-plans list, so when the number looks off you're one tap from the plans that drove it.
Closing a plan feeds the record
At end of day a foreman or PM closes the plan and enters what actually got installed against each activity, with a one-line variance reason where the day didn't go to plan. They can also enter an actual-hours correction — but that needs its own reason and, again, it adjusts the plan's record, not the compliance KPI. Anyone who can manage plans can close them, and the foreman who authored a plan can always close their own.
What next?
Compliance tells you the past 30 days; look-ahead tells you the next six weeks: Look-Ahead →
Frequently asked
What exactly does plan compliance divide?
Approved hours worked on planned activities over the last 30 days, divided by the planned crew-hours (crew size × hours per person) for those plans. Above 100% means more was worked than planned; below means the plan is slipping.
Can the hours correction at plan close-out change the KPI?
No. The actual-hours correction a PM can enter when closing a plan adjusts the plan's own record only. The compliance KPI always reads genuinely approved hours, so it can't be inflated at close-out.
Do reserved draft entries count toward compliance?
Not until they're approved. Sharing a plan can pre-create blank-hours placeholders so clock-ins land in the right place, but they only contribute once a foreman approves the real hours.
Who can see plan compliance, and who can close plans?
Everyone on the project can see the KPI (it respects project access). Anyone who can manage daily plans can close them, and the foreman who authored a plan can always close their own.
Is the window always 30 days?
30 days is the default rolling window shown on the dashboard. The underlying report accepts a custom window if you need a shorter or longer view.